On 4/20/2017 12:05 PM, Chapman Flack wrote:
> You should be able to build for 9.6 by checking out the
> REL1_5_STABLE branch. There's an outstanding issue involving
> pg_upgrade that I still have to look at, but if you don't run
> into that you should be ok.
ok, thanks, that worked (at least, its compiled and installed... I'm
leaving it up to the app developer to do the final testing)
--
john r pierce, recycling bits in santa cruz