Back in 2002, Jean-Luc Lachance gave a nifty algorithm
(http://archives.postgresql.org/pgsql-sql/2002-06/msg00301.php) for
determining the resulting date given a starting date and number of
'workdays' in the future. The trick was that weekends (Saturday and
Sunday) could not be counted.
The algorithm looks like this:
date := now - day_of_the_week
interval := interval + day_of_the_week
date := date + int( interval/5)x7 + ( interval mod 5)
However, when I attempted to implement it, I found the answers I received to be problematic.
I'm sure the issue is in my interpretation of the algorithm, but I can't quite figure it out.
Let's take an example. Starting on March 11, 2005, what date is 4 'workdays' in the future?
Step one:
date := now - day_of_the_week
March 5th = March 11th - 6 (6 is the day of week for Friday....march 11th).
Step two:
interval = interval + day of the week
10 = 4 + 6 (4 is the interval)
After this point, the date field is now March 5th and the interval is now 10.
Step three:
date := date + int( interval/5)x7 + ( interval mod 5)
March 19th = March 5th + 14 + 0
End result.....March 19th.
But March 19th is not correct (heck, it's a Saturday!). It should be March 17th.
What am I doing/interpreting wrong?
From | Date | Subject | |
---|---|---|---|
Next Message | Miroslav Šulc | 2005-03-14 14:05:30 | Re: free space map settings |
Previous Message | go | 2005-03-14 13:52:58 | free space map settings |