Heikki Linnakangas wrote:
> Simon Riggs wrote:
> > My thinking is to move to a two stage release process: Do one
> > "production" release annually, and one "dev" release at the 6 month
> > mid-point. That way each new release contains a manageable number of new
> > features and we have a realistic chance of integrating them
> > successfully. Support companies would then have the option to support
> > both releases, or just the main production release. Leading edge users,
> > of which we have many, would then benefit from more frequent additional
> > features.
>
> I like the idea of draining the patch queue mid-way through the release
> cycle. That'll hopefully encourage people to submit patches earlier in
> the release cycle, knowing they will be reviewed. It'll also give people
> working on external projects, drivers and tools, a checkpoint to sync with.
Aside from a few complex patches all the patches in the queue are from
work completed just before feature freeze --- we have been draining it
during the entire release. I think for the few complex patches that
have been in there for a while, the problem is that reviewing them is
going to be so hard, no one has done it. Now that we are in feature
freeze, we have to do it --- but the idea that we have somehow just been
holding patches during the whole release isn't true.
--
Bruce Momjian <bruce(at)momjian(dot)us> http://momjian.us
EnterpriseDB http://www.enterprisedb.com
+ If your life is a hard drive, Christ can be your backup. +
From | Date | Subject | |
---|---|---|---|
Next Message | Bruce Momjian | 2007-04-30 11:15:22 | Re: Feature freeze progress report |
Previous Message | Bruce Momjian | 2007-04-30 11:06:55 | Re: Feature freeze progress report |
From | Date | Subject | |
---|---|---|---|
Next Message | Bruce Momjian | 2007-04-30 11:15:22 | Re: Feature freeze progress report |
Previous Message | Bruce Momjian | 2007-04-30 11:06:55 | Re: Feature freeze progress report |