On Tue, 10 Jun 2003, Tom Lane wrote:
> Bruce Momjian <pgman(at)candle(dot)pha(dot)pa(dot)us> writes:
> > We are 5 days away from the feature freeze date, but with the almost
> > week of downtime we have had, I don't think we can stick to that date.
> > Do we choose July 1 as feature freeze and July 15 as beta, or push beta
> > start to Auguest 1?
>
> I don't think a week of partial downtime justifies a month's slip.
>
> The July 1/15 schedule seems like it might be a good plan though.
> I know I'm not going to be done editing error messages by June 15 ...
July 1/15 sounds good to me as well ...